Home > Completed Projects

S. No.TYPE OF PROJECTNAME AND LOCATION OF PROJECTCLIENT ASSOCIATEDDURATION OF PROJECT
1Fabrication and Erection of Mould for Segment and Launching girder etc.
(2000 MT)
8 Lane Kim Expressway Vadodara to Mumbai. Extra-dosed Cable Stay Bridge, Narmada River Bharuch, Gujarat. Ashoka Buildcon Limited May 2018 to July 2020
2Fabrication and Erection of Double-D Cutting Edge, Straight and Curve Shuttering, Barge,Fabrication of Well Cassion and Erection of Cassion while floating in water, Cribs, Truss and Gantry for Cassion.
(1000 MT)
Rail Cum Road Bridge Over River Ganga Between Ghazipur and Tarighat, Ghazipur, U.PS. P. Singla Constructions Pvt. Ltd.Nov. 2017 To Dec. 2018
3Fabrication and Erection of Mould for Segment Casting, Wing Shutter, Truss, Cribs, Box Culvert Shutter.
(400 MT)
Zuari Bridge Project, Goa Dilip Buildcon Limited Nov. 2017 To June 2018
4Fabrication and Erection of Cribs and Truss, Steel I-Girder, Straight and Curve Shuttering, Pier shaft and Pier cab etc.
(700 MT)
3 Km, Six Lane Fly Over Khamanon Site, on Ludhiana and Chandigarh National Highway Punjab. Ashoka Buildcon Limited August 2017 To Dec. 2018
5Fabrication and Erection of shuttering plates (I-girder & circular pier plates, well curb, staining etc.
(500 MT)
Four Lane with paved shoulder of Varanasi to Gorakhpur, UP PNC Infrarech Limited July 2017 To Dec 2018
6Fabrication and Erection of Cutting Edge, Mould for Segment, Truss and Cribs and All type Shuttering etc.
(100 MT)
Long Span High Level Road Bridge over River Teesta near Haldibari, Coochbehar ( West Bengal) S. P. Singla Constructions Pvt. Ltd.March 2017 To Feb. 2018
7Fabrication and Erection of Cutting Edge, Straight and Curve Shuttering, Barge, Well Cassion and Erection of Cassion while floating in water.
(800 MT)
Dedicated Freight Corridor Corporation of India Ltd. Railway Bridge over Yamuna, Allahabad, U.P. GMR GroupSep. 2016 to April 2018
8Fabrication and Erection of Liner, I-Girder, Shuttering of Pier and Pier Cap etc.
(600 MT)
Two Lane Highway Bridge at R-Block Patna, Bihar. Rachana Construction CompanyMay 2016 To April 2017
9Fabrication and Erection of Mould for Segment Casting.
(380 MT)
Eastern Periphery Expressway, Faridabad, Haryana. BridgeCon India January 2016 to May 2016
10Fabrication and Erection of Liner, Pier and Pier Cap Shuttering, Box Girder, etc.
(500 MT)
ROB for Rail Cum Road Bridge on River Ganga Digha Ghat, Sonepur, BiharS. P. Singla Constructions Pvt. Ltd.Jan. 2016 To Dec. 2017
11Fabrication and Erection of Liner for piles, Mould for Segment, Pier Diaphagram Shuttering upto Pylon and Launching Girder with Slider etc
(1200 MT)
4 Lane Extra – Dosed Cable Stayed Bridge with Footpath across River Ganga, Ballia, U.PATEPL – SPSCPL Joint Venture May 2015 To Nov. 2017
12Fabrication and Erection of Cutting Edge, Box Girder, Launching Girder etc.
(1000 MT)
Railway Bridge across River Dehri-on-Sone Arvind Techno Engineers Pvt. Ltd. And MG Construction Pvt. Ltd. Jan. 2014 To March 2015
13Fabrication and Erection of Liner, Mould for Segment , Pier and Pier Cap Shutter and Launching Girder.
(2000 MT)
Bridge at Kolaghat over Roopnarayan river, West Bengal Arvind Techno Engineers Pvt. Ltd. Completed 31 March, 2013
14Fabrication and Erection of Cutting Edge, Pier and Pier Cap Shutter, Mould for Segment.
(800 MT)
HL RCC Bridge over Koshi River, Saharsa, Baluaghat, Bihar S. P. Singla Constructions Pvt. Ltd.Completed 31 Dec. 2013
15Fabrication and Erection of Ground Support Launching Girder.
(350 MT)
KMRC Project Rajrahat, New Town, Kolkata.AFCONS Infrastructure Limited July 2013 To Dec. 2013
16Fabrication and Erection of Cutting Edge, Box Girder, Launching Girder, etc.
(700 MT)
Highway Bridge, Kishanganj, Bihar. S. P. Singla Constructions Pvt. Ltd.June 2013 to June 2016
17Fabrication and Erection of Mould for Segment, Launching Girder etc.
(600 MT)
Flyover on Jagdev path, Shekhpura, Patna, Bihar Ranjit Buildcon Ltd. July 2012 To March 2013
18Fabrication and Erection of Cutting Edge and Shuttering Plates.
(450 MT)
Bridge over the Son river, District Arwal, Bihar S. P. Singla Constructions Pvt. Ltd.Oct 2009 To March 2011
19Fabrication and Erection of Double-D Cassion Cutting Edge and Shuttering Plate of Pier and Pier Cap.
(400 MT)
Rail-cum-road bridge across Ganga river, Khagariya and Munger, Bihar. Arvind Techno Engineers Pvt. Ltd. June 2009 To March 2010
20Fabrication and Erection of Double-D Cutting Edge, Shuttering Plates and Mould For Segment, Truss and Cribs etc
(560 MT)
ROB in Lieu of Level Xing No. 92 in Siwan Station Yard, Bihar. S. P. Singla Constructions Pvt. Ltd.May 2008 To May 2009
21Fabrication and Erection of Cutting Edge, Caisson, Barges and Launching Girder
(900 MT)
Bridge over the Yamuna river, Kalpi, District Jalaun, UP Arvind Techno Engineers Pvt. Ltd. Sep. 2006 To Dec. 2007
22Fabrication and Erection of Cutting Edge, Shuttering Plates
(70 MT)
NH 3 & 4, Lucknow to Faizabad HCC Limited Aug. 2006 To March 2007
23Fabrication and Erection of Structure Staging.
(250 MT)
Glycols Ethar Plant, Kashipur, UttrakhandIndia Glycols Ltd. Feb. 2006 To March 2006
24Fabrication and Erection of Stop log gates, Trash rack, Super Structure, Cable rake, Duct:- Circular and Rectangular.
(1000 MT)
SBC Project, District Surendar Nagar, Gujarat HCC Ltd. Nov. 2005 To Oct. 2008
25Fabrication of Shuttering Plates.
(350 MT)
NH24, Moradabad to Garhmukteshwar, District Moradabad, UP PNC Ltd. April 2005 To Sep. 2005
26Fabrication and Erection of Super Structure for Distillation Tower.
(500 MT)
India Glycols Ltd., Gorakhpur Essar Technocrates and Engineers India Pvt. Ltd. Essar Technocrates and Engineers India Pvt. Ltd.
27Fabrication of Shuttering Plates and Mould for Segment.
(450 MT)
Delhi Metro Rail Project, Mundka, New Delhi. I.J.M Corporation and Bridgecon India April 2005 To Sep. 2005
28Fabrication of Shuttering Plates and Staging
(62 MT)
Gujarat State Highway (GSHP 6), Sidhpur District Patan, GujaratHCC Limited July 2004 To Sep. 2004
29Fabrication and Erection of Cutting Edge and Shuttering Plates.
(260 MT)
Aqueduct over Hiran river, Jabalpur, MP S. P. Singla Constructions Pvt. Ltd.Jan. 2004 To March 2004
30Fabrication and Erection of Cutting Edge and Shuttering Plate for Pier and Pier Cap.
(250 MT)
Railway Bridge on Ganga River, Garhmukteshwar, District Ghaziabad, UP S. P. Singla Constructions Pvt. Ltd.April 2004 To Oct. 2004
31Fabrication and Erection of Cutting Edge, Shuttering Plates and Launching Girder.
(1200 MT)
Bridge on Dehri on Sone river, District Aurangabad, Bihar NCC Ltd. And Arvind Techno Engineers Pvt. Ltd. April 2003 To March 2004
32Fabrication and Erection of Cutting Edge and Shuttering Plates.
(75 MT)
Railway Bridge on Pachranga river, Jalandhar, Punjab. S. P. Singla Constructions Pvt. Ltd.Feb. 2003 To April 2004
33Fabrication and Erection of Cutting Edge and Shuttering Plates.
(90 MT)
Railway Bridge on Ganga river, Khatoli District Muzaffar Nagar, UP S. P. Singla Constructions Pvt. Ltd.Jan. 2003 To March 2003
34Fabrication of Shuttering Plates.
(50 MT)
N.H. VA Aurangabad, Bihar Oriental Structural Engineers Ltd. Jan. 2002 To Feb. 2002
35Fabrication and Erection of Cutting Edge and Shuttering Plates.
(560 MT)
Bridge on Lila Jain river, NH2 VA Sherghati District Gaya, Bihar Gammon India Limited Feb. 2002 To Dec. 2002
36Fabrication and Erection of Cutting Edge and Shuttering Plates.
(95 MT)
Kanpur to Lucknow Rana Construction Ltd. June 2001 To Aug. 2001
37Fabrication and Erection of Cutting Edge and Shuttering Plates.
(290 MT)
Railway Bridge on Yamuna river, Etawa, UP. Arvind Techno Engineers Pvt. Ltd. Nov. 1999 To April 2000
38Fabrication and Erection of Cutting Edge and Shuttering Plates and Staging.
(360 MT)
Railway Bridge on Tawi river, Udampur, Jammu. Arvind Techno Engineers Pvt. Ltd. Oct. 1999 To March 2000
39Fabrication and Erection of Cutting Edge and Shuttering Plate for Pier and Pier Cap.
(60 MT)
Railway Bridge Nangloi, New Delhi Arvind Techno Engineers Pvt. Ltd. Oct. 1999 To Nov. 2000
40Fabrication and Erection of Structural Staging and Column and Truss.
(1200 MT)
Dewan Sugar Mill Aghwanpur Dist. Moradabad and Chadha Spintax Ltd. Gajraula Dist. Moradabad Era Constructions (India) Ltd. Feb. 1995 To March 1996
41Fabrication and Erection of Pipelines, Structural Staging, Column and Truss.
(440 MT)
D.S.M Sugar Mill Asmoli Dist. Moradabad D.S.M Sugar, Asmoli (A Unit of the Dhampur sugar mills Ltd.) June 1994 To Dec. 1994

About Us

Structural Steel Design, Fabrication, Erection and Concrete Casting of the equipment's used in Railway and Highway Bridges, Flyovers, Elevated Corridors for Metro, Superstructures and Industrial Plants.

Our Services

  • Structural Steel Design Engineering
  • Structural Steel Fabrication
  • Structural Steel Erection
  • Concrete Casting

Useful Links

  • Home
  • About Us
  • Our Projects
  • Services
  • Contact Us

Follow Us

info@hindinfratech.in Drop Us a Line
+91-8630062508 Call Us Now
400, Batwal Bijnor Road, Pakka Bagh Amroha - 244221 Uttar Pradesh, India
Copyright © 2021 Hind Infratech Engineers - All Rights Reserved
AKS WebSoft Consulting Pvt. Ltd.